Stucco

Not only did the cinder block replace the old damaged adobe, when it reached the roof line it the contractor tied or connected the roof to the new outside layer of brick so that the whole building is tied together.



On the front or north side of the building where they did not need to go all the way up with new cinder block there places where you could see how the old and new bricks all came together, where the old stucco had cut away.


I was surprised how thick the stucco layer was over the top of the brick.



You can see where a lot of the wood had been removed from under the roof, all the trim was also removed. It ended up being stored in the chapel until we had Living Home Construction & Design, come out to sort through everything.  Some of the trim was damaged when removed and some was too weather worn to reuse.  The good stuff was cleaned up and had a primer coat put on it until time for it to put back on along with the new milled pieces.


The wood trim will have to wait until the new stucco has been completed though.  The first layer of which went on last week.





On With the New

After the damaged layers of brick were removed the entire west wall had scaffolding put up around it  and then the whole thing was tented to keep out the elements and control the temperature.


To both provide a base for the new cinder block and to firm up the old stone foundation a wet slurry was poured and re-bar mounted into the foundation to reinforce the wall.  Then the new brick started  to be layered up along side the old adobe.



Every four feet there was a back fill of mortar and all the cells of the cinder block were also filled with with mortar.  So the wall went up pretty fast, four feet of brick, back fill and then repeat.  The tough part was when they got to the top and there was only enough room to squeeze in at an angle with hose from the pumper truck to get the mortar in for the back fill.


Off With the Old

The building was used as an LDS chapel until the mid 70's.  (It still has the same orange-gold carpet to prove it.)  During that time every president of the church from Brigham Young to David O. McKay spoke in the chapel.

At one time it was used as a mortuary.  Only for funerals and viewings, they did not do any embalming or body preparation there.  After that two other families owned the building and used it as a residence but no one ever did anything much with chapel.  Although all the stained glass is gone and all but one of the benches in the chapel are gone, the chapel organ is still there though.  There was a class room wing added to the chapel in either the 40's or 50's.  The Sunday school room on the east end of the wing has been turned into a two bed room apartment along with one of the class rooms.  So there has been a lot of projects started and stopped, the plumbing and electrical in the basement show the proof of that.  Yes it has a basement that goes under about 2/3 of the class room wing.  Aside from having relics left from its old coal fired boiler for heating days days like a coal room and the old plate steel and cast iron doors for the furnace, it has 10 foot ceilings.

The first project that need to be handled was and is repairing the damage to the exterior adobe brick walls of he chapel.


We checked with Utah Historical Society to find out what would be an acceptable to repair the walls and still retain its historical status.  We found that since it has a stucco finish, the damaged adobe could be replaced with cinder block and then stuccoed over as long as we retain the original look of the building.

The next problem was finding a contractor that would be willing to take on the project.  I took pictures and emailed a dozen contractors that did stuff sort of like this or said their web sites.  None of them replied back.  Finally, again the Historical Society, I got a hold of Abstract Masonry, who specialize in historic masonry restoration.  They along with Ensign Engineering started to do some exploratory work to see what they were up against.  After ward we were able to breath a little easier when they came back with their findings.  The walls are 32" thick adobe and the adobe brick is unusually hard.  The foundation is about 42" thick and 48" high with about 36" under ground and was made of hard stone that was not prone to easy deterioration.  Also the wall had already been repaired, twice we later found out, with cinder block.

Unfortunately, all the aspens along the west wall had to come down for the construction, they were also suspected in the cause of the one of the problems, too much watering and adobe/mud brick do not mix.  The engineer also wanted supports in side the chapel to hold the roof up just in case.



Then the damaged adobe and the old cinder block came down.


We Bought a Church

Quite awhile ago we heard about this old church being up for sale.  It took along time to get a bank to approve the loan to buy it and to get financing to do the repairs needed.  The chapel walls are made of adobe brick and are 32 inches thick but due to water damage over the years, the outside layers began to fail in several places.

The historical marker outside of the church is for the old Grantsville Fort. 


The chapel part of the church was inside the fort walls.


The plaque on the chapel tells the year it was built, 1866.


The rosette medallions used to have kerosene chandeliers hanging from them.